top of page

The Youth Anchor, Church End
Expected Completion: Summer 2026
About The
Project
The Youth Anchor, Church End is Brent’s first new youth facility in over a decade, delivered by, Young Brent Foundation, United Borders and funded by Brent Council and GLA, built by I O Together Spaces Ltd.
​
With £920,000 secured, it is transforming 483–485 High Road into an inclusive space for young people aged 16–25, featuring learning and wellbeing zones, therapy rooms, and a community coffee bar — empowering youth through creativity, enterprise, and connection.
Project Timeline
![]() September 2026HVAC has started to be installed. | ![]() August 2026Kayziahs summer placement with us ends as she prepares to go back to college. | ![]() August 2026HVAC delivery arrived for installation to start. | ![]() August 2026The continuation of plastering the curves in each room |
|---|---|---|---|
![]() August 2026Cable trays going up ready for HVAC to come in | ![]() August 2026The continuation first fix electrical work, installing the backboxes | ![]() August 2026Our trainee site workers learnt how to use the sanding machine. | ![]() July 2026Our site team are filling the gaps between the boards ahead of them being plastered. |
![]() July 2026We welcomed three students for a week working in the office and on site for their work experience. | ![]() July 2026Started adding insulation into the framed out walls. | ![]() July 2026Kayziah joins us for a Youth Summer Takeover of our social media. | ![]() June 2026The beginning of first fix electrical work, starting off with wiring. |
![]() June 2026Installing first fix plumbing | ![]() May 2026Brick walls erected. | ![]() May 2026Framing and boarding continues including the ceiling | ![]() April 2026We continued framing the rest of the ground floor, mapping out each room according to the floor plan. |
![]() March 2026We began welcoming young people to work with us as part of their school work experience weeks. | ![]() March 2026We also had the pleasure of having a visit from Jason Roberts. | ![]() February 2026Visiting our suppliers at the Workspace Design Show. | ![]() February 2026Sourcing suppliers for the build and fit out of the Youth Anchor |
![]() February 2026Behind the scenes of United Borders filming their naming video for the Youth Anchor to released in the Summer. | ![]() February 2026The project moved into the next phase of build-out and space definition as we continued to frame and board the rooms on the ground floor adjusting them slightly. | ![]() February 2026Boarding of internal rooms began. | ![]() January 2026Internal framing works commenced, marking the start of spatial transformation within the building. |
![]() January 2026Additional site surveys conducted. | ![]() December 2025United Borders hosted Hellman & Friedman on site as part of a fundraising away day, showcasing the vision and progress of The Youth Anchor. | ![]() December 2025Slab levelled in preparation for fit-out. | ![]() December 2025Strip-out works completed. |
![]() November 2025Working out the correct spacing for the toilets and the dimensions for the wellness space. | ![]() November 2025Rough design begins with the mapping out of the entire space. | ![]() November 2025External window hoarding installed to secure the building and prepare for construction. | ![]() November 2025Strip-out works began. |
![]() November 2025Site surveys completed | ![]() October 2025Contract signed and project onboarding commenced. Project team and key stakeholders were confirmed. A public press release announced the project, led by the Council in partnership with stakeholders. | ![]() September 2025Successfully awarded the tender to deliver The Youth Anchor project. |
March 2025
Submitted the first draft project brief as part of the competitive tender process, outlining the vision, impact, and delivery approach for The Youth Anchor.
bottom of page







































