top of page
IMG_6863.HEIC

The Youth Anchor, Church End

Expected Completion: Early 2027

About The
Project

The Youth Anchor, Church End is Brent’s first new youth facility in over a decade, delivered by, Young Brent Foundation, United Borders and funded by Brent Council and GLA, built by I O Together Spaces Ltd.

​

With £920,000 secured, it is transforming 483–485 High Road into an inclusive space for young people aged 16–25, featuring learning and wellbeing zones, therapy rooms, and a community coffee bar — empowering youth through creativity, enterprise, and connection.

Project Timeline

October 2026

October 2026

Installation of internal door frames commenced, helping to define the connections between spaces. The example pictured shows the doorway linking the staff room to the food preparation and coffee area.

October 2026

October 2026

Mock furniture arrangements were set up in the rooms to assess how the proposed layouts work in practice, ensuring the spaces are functional and make effective use of the available space.

October 2026

October 2026

Paint samples are being applied to the walls to assess how the colours selected from the mood board translate into the physical space under real lighting conditions.

October 2026

October 2026

All ground floor rooms are being wired with plug socket outlets.

September 2026

September 2026

Rendering has begun on the external walls surrounding the multi-use open space.

September 2026

September 2026

The external walls of the meeting rooms and café restrooms have now been rendered.

September 2026

September 2026

Several rooms have now received their mist coat, while HVAC installation is continuing throughout the space.

September 2026

September 2026

Fixtures and fittings have started to arrive on site.

September 2026

September 2026

All rooms that have been filled and sanded are now beginning to receive their mist coat.

September 2026

September 2026

All ground-floor walls within the multi-function space have begun to be levelled in preparation for the construction of the mezzanine floor.

September 2026

September 2026

HVAC installation has now begun.

August 2026

August 2026

Kayziah’s summer placement with us has now come to an end as she prepares to return to college.

August 2026

August 2026

The HVAC system has been delivered to site, ready for installation to begin.

August 2026

August 2026

Plastering of the curved walls in each room is continuing.

August 2026

August 2026

Cable trays are being installed in preparation for the HVAC system.

August 2026

August 2026

First-fix electrical work is continuing, including the installation of back boxes.

August 2026

August 2026

Our trainee site workers received hands-on training on how to safely and effectively use the sanding machine.

July 2026

July 2026

Our site team are filling the gaps between the boards in preparation for plastering.

July 2026

July 2026

We welcomed three students for a week of work experience, gaining valuable insight both in the office and on site.

July 2026

July 2026

Insulation has started to be installed within the framed walls.

July 2026

July 2026

Kayziah joined us for a Youth Summer Takeover, taking over our social media channels for the summer.

June 2026

June 2026

First-fix electrical work has begun, starting with the installation of wiring.

June 2026

June 2026

First-fix plumbing installation is now underway.

May 2026

May 2026

The brick walls have now been erected.

May 2026

May 2026

Framing and boarding works are continuing, including installation to the ceiling.

April 2026

April 2026

Framing continued across the remainder of the ground floor, setting out each room in line with the floor plan.

March 2026

March 2026

We began welcoming young people to join us for school work experience placements, giving them the opportunity to gain hands-on experience in the workplace.

March 2026

March 2026

We also had the pleasure of welcoming Jason Roberts for a visit.

February 2026

February 2026

We visited our suppliers at the Workspace Design Show.

February 2026

February 2026

We began sourcing suppliers for the build and fit-out of the Youth Anchor.

February 2026

February 2026

Behind the scenes with United Borders as they filmed the Youth Anchor naming video, which was set to be released in the summer.

February 2026

February 2026

The project moved into the next phase of the build-out, with framing and boarding continuing across the ground-floor rooms and minor adjustments made to refine the layout.

February 2026

February 2026

Boarding of the internal rooms has now begun.

January 2026

January 2026

Internal framing works commenced, marking the beginning of the building’s internal transformation and defining the new spaces.

January 2026

January 2026

Additional site surveys were carried out to support the next stages of the project.

December 2025

December 2025

United Borders hosted Hellman & Friedman on site as part of a fundraising away day, providing an opportunity to showcase the vision for The Youth Anchor and the progress made so far.

December 2025

December 2025

The slab was levelled in preparation for the fit-out works.

December 2025

December 2025

Strip-out works have now been completed.

November 2025

November 2025

The layout and spacing for the toilets were reviewed, alongside confirming the dimensions of the wellness space.

November 2025

November 2025

Initial design work began with mapping out the layout of the entire space.

November 2025

November 2025

External window hoarding was installed to secure the building and prepare the site for construction works.

November 2025

November 2025

Strip-out works commenced on site.

November 2025

November 2025

Initial site surveys were completed to assess the space and inform the next stages of the project.

October 2025

October 2025

The contract was signed and project onboarding commenced. The project team and key stakeholders were confirmed, followed by a public press release announcing the project and the Council’s partnership with key stakeholders.

September 2025

September 2025

We were successfully awarded the tender to deliver The Youth Anchor project.

March 2025

Submitted the first draft project brief as part of the competitive tender process, outlining the vision, impact, and delivery approach for The Youth Anchor.

Project Partners

1.png

Young Brent Foundation

Client & Operator

3.png

United Borders

Delivery Partner

5.png

I O Together Spaces

Principal Contractor

2.png

Brent Council

Funder and Strategic Lead

TYA Partner Logos.png

Mayor of London & The Local Enterprise Partnership for London

Funder

Innovative Opportunities LTD

Head Office Address:

16 Neasden Lane, NW10 2TS

 

Email: hello@ioldn.com

​

​

Company Registration Number 13880614​

Thanks for submitting!

  • Facebook
  • LinkedIn
  • Instagram
9300 Business Climate Charter logo 2026.jpg
brent good work logo.jpg
Innovative Opportunities LTD
Company Number 13880614

© 2026 by Innovative Opportunities LTD

bottom of page